Migration of Large Network Infrastructure for a Leading American Telecoms Company

Reviewing and completing a complex handback plan and then project managing its execution


Our client provides communications, technology, information, and entertainment products and services to business, consumers, and government entities. They serve small and medium businesses, global enterprises, public sector, and wholesale customers across multiple geographies.


The client was required to complete and execute a handback plan for a major company which provides critical energy infrastructure to millions of people across the UK and US. This company had previously been outsourcing the management of its network infrastructure to our client, but were planning to bring this back inhouse following the fulfilment of its previous contract.


Specialist support was required to update the handback plan and agree with the end client on its terms, before ultimately executing this plan. Cambridge Management Consulting was engaged to project and programme manage the fulfilment of these contractual obligations across multiple regions, stakeholders, and workstreams.

Download the Full Case Study


Contact Form - Project Management of a Network Migration

The

Challenge


This engagement was comprised of two stages. The first stage was to support the client with its commercial and contract management to formally update and agree on a handback plan with the end client. As the contract was imminently reaching the end of its term, this was a time-bound critical contractual obligation, and it was important that the plan was current and formally agreed upon to ensure that there was no impact to crucial service delivery caused by the ultimate network migration.


The second stage involved the execution of the handback plan itself between the two parties. This ran for 18 months (plus a further 6-month readiness planning period). The delivery comprised a global, complex programme plan with multiple stakeholders and nine major workstreams delivered using an agile methodology.

Given the project’s complexity and the criticality of the end client’s services, executing both stages of this challenge required an acute and robust understanding of the contract and agreement of its obligations. This involved reviewing historical issues to understand risk, finalising the scope and delivery timeline, and defining the governance structure to ensure that progress during and beyond the contract scope remained intact and consistent.

Our

Solution


Contract Review


Cambridge MC recommended an Agile approach to programme management delivery for both elements of the engagement. We reviewed the current status of the handback documentation and built a new and refreshed handback plan in iterative steps, annex by annex, sharing drafts for approval at regular intervals as the commercial, technical, and legal aspects evolved.

In order to eliminate potential risks and issues early, we shared a draft of the handback plan halfway through the initial phase of this engagement to encourage review and feedback. This allowed for a more tailored refinement and richer data analysis to be included in the final document, as well as the avoidance of surprises or issues occurring in the final stages. This meant that the documents were ultimately approved quickly and directly when it came to formal approval.


The Handback


The programme management of the handback execution continued these same principles of collaboration and transparency, crucial qualities for service transitions and migrations of this nature in order to ensure a seamless transition to minimise service impact. Due to the volume and complexity of the network infrastructure to be migrated, it was also important to maintain flexibility and adaptability throughout the sprint cycles, as there were numerous deliverables all independently reliant on a combination of the client’s due diligence and support on device history and status, as well as the end client’s readiness to accept and test them.


Throughout this process, we ensured that collaboration and open communication were at the heart of the entire project lifecycle, setting guarantees that everyone was continually briefed and comfortable with the direction, pace and end goal, and that any risks and issues were addressed and resolved early.

TheTeam


The programme management team engaged on this project was led by Kirsten Watson, Partner – Contract Management at Cambridge Management Consulting. With nearly three decades of experience managing major contracts across a variety of market sectors, Kirsten is an expert in programme and project management, risk management, client and stakeholder management, collaboration, and relationship management.


Kirsten has a proven track record designing comprehensive plans and workstreams with robust governance and transparent communication in order to ensure alignment between clients and stakeholders towards an agreed goal.

Outcomes & Results


1

700 Sites

Cambridge Management Consulting successfully supported the client with the migration of over 700 sites in the UK and US, comprising thousands of network devices, to its end client’s network operating centre.

2

Knowledge Transfer

We completed a comprehensive knowledge transfer across operational and security environments, assisting the end client to quickly build understanding and develop its own processes and procedures. 

3

Intellectual Property Rights

We ensured that the protection and ringfencing of intellectual property Rights was handled sensitively so that the end client was provided with a working network knowledge and expertise without compromising our client’s product and offering.

4

Project Management of HR Functions

We also oversaw the project management of all HR aspects throughout the handback, ensuring that the necessary briefing and engagement of key parties was fulfilled with respect to employment laws and obligations for employees impacted by the transition.

5

End-Client Utilised Our Project Manager

Due to the team’s meticulous attention to detail across all work packages and comprehensive tracking, the end client chose to stand-down its third-party consultants and co-utilised Kirsten as the overall Programme Director.

Get in touch with our Project Management Experts


We are a highly collaborative team of senior-level executive professionals able to adapt to any challenge, however niche & challenging.

+44 (0)1223 750335

info@cambridgemc.com

Contact Form - Data Centre Due Diligence Case Study

Case Studies


Our team has had the privilege of partnering with a diverse array of clients, from burgeoning startups to FTSE 100 companies. Each case study reflects our commitment to delivering tailored solutions that drive real business results.

CASE STUDIES

A little bit about Cambridge MC


Cambridge Management Consulting is a specialist consultancy drawing on an extensive global network of over 220 senior executives in 26 countries.


Our purpose is to help our clients have a better impact on the world.

ABOUT CAMBRIDGE MC

Industry Insights


Visualisation of Earth with lines of data wrapped around it
by Eric Green • 4 November 2026
PROCUREMENT & AI | Neoscalers often buy the network last, under pressure. Eric Green explains the contract-term and cost risks, and how procurement discipline closes the gap | READ FULL ARTICLE NOW
30 October 2026
23 October 2026, Cambridge – Cambridge Management Consulting (Cambridge MC) has celebrated its annual corporate Green Day, bringing colleagues together for a day of environmental volunteering instead of a day in the office. On Friday 23 October, the international management consultancy, headquartered in Cambridge, teamed up with Cambridge City Council to improve wildlife habitat at Cherry Hinton Hall, a 12-hectare public park in south-east Cambridge. Working alongside the City Council’s Community Engagement team, the Cambridge MC team focused on the glade in the nature area at the rear of the park, cutting back grass, clearing away the cuttings, and sowing wildflower seeds. The work was designed to support the management of the green space and create better conditions for wildlife, while giving Cambridge MC colleagues a direct role in caring for their local environment. Tim Passingham, founder and executive chairman of Cambridge MC, explained: “Making a positive impact means being prepared to roll up our sleeves and contribute to the communities in which we work. Rather than treating environmental responsibility as an abstract corporate ambition, Green Day gives our colleagues the opportunity to contribute their time and effort to community green spaces – turning our commitment into something tangible by working alongside our local community, supporting the places we share and recognising that small, practical actions can make a difference when we take them together. “The initiative also reflects the importance of collaboration in environmental action. Individual volunteers, community groups, businesses, and local authorities all have an important role to play in maintaining accessible green spaces and supporting urban biodiversity.” While Cambridge was the focus of the company-wide initiative, Green Day extended beyond the city, with events taking place in the New Forest, and planned initiatives in London which were unfortunately cancelled due to adverse weather. In the New Forest, Cambridge MC colleagues worked with local environmental group ECO SWAY on preparing shared green spaces and planting pollinator-friendly bulbs to support bees and butterflies in the spring. Unfortunately, the London team’s efforts were cancelled due to Storm Austen, however they were excited to be joining local volunteers from Stoke Newington Urban Green (SNUG) to water and mulch young trees ahead of winter, helping them to establish and reach maturity. As an international consultancy, the team’s environmental efforts did not stop there. In France, one Managing Partner contributed to his local ecosystem by planting an oak tree, and in Portugal another Partner showed her support by planting several fruit trees. Elsewhere, consultants based outside of the UK or simply unable to travel to the three primary locations sowed tree bombs as a remote way of amplifying the day’s overall mission. Green Day forms part of Cambridge MC’s wider commitment to using its expertise, time, and resources to create positive impact. The purpose-beyond-profit company commits at least 10% of its profits to charitable causes that tally with its ‘Five Cs’: Children (and young people), Conservation (and sustainability), Cancer, Communications, and Cambridge (the Cambridge ecosystem). Alongside financial support, Cambridge MC also engages in purposeful pro bono work, gifting at least 1% of its time and expertise to help charities mature, digitalise, and reduce costs. And, uniquely, the company holds 1% of its equity in reserve for charitable use should an equity event occur. In September, Cambridge MC achieved Certified B Corporation status, marking a significant milestone in the company’s commitment to responsible business and recognising its approach to creating value for its team, clients, community, and the environment alongside commercial success. Tim said: “Our approach recognises that a responsible business is not defined solely by the advice it gives clients, but also by the contribution it makes to the communities and environments in which it operates. “By combining hands-on work with local partners across Cambridge and the New Forest, the Green Day initiative is bringing this principle to life – one green space at a time.”
A neon wireframe view of a city with roads and bridges.
by Paul Brooker • 15 October 2026
Sales Transformation | Manual workarounds and fragmented systems are costing telecom operators revenue and margin. Discover how to remove the Complexity Tax and unlock value | READ FULL ARTICLE NOW
Statue of justice with neon overlay.
by Greg Mook • 7 October 2026
Greg Mook sets out the ten capabilities communications providers need for effective compliance, from business accountability to delivery-chain assurance | READ FULL ARTICLE
Sunrise over the ocean.
24 September 2026
Cambridge Management Consulting has achieved Certified B Corporation status, validating its commitment to responsible business and long-term stakeholder value | READ THE FULL PRESS RELEASE
A long  bank of solar panels in a field at dusk
by Scott Armstrong • 4 August 2026
ESOS Phase 4 isn't just compliance. Scott Armstrong explains why cheap audits cost more long-term, and how to treat Phase 4 as a strategic energy opportunity | READ FULL ARTICLE
Neon waves and lines with overlay of white plus signs, some dissolving away
by Jason Jennings • 14 July 2026
Procurement | Most organisations are sitting on 3–8 per cent of recoverable third-party spend. Here's where AI-powered spend analysis finds it — and how CFOs can act without cutting into operations | READ FULL ARTICLE
Three interlocked rings, silver, on a back background.
by Ruth Redding • 9 July 2026
Leadership & Change | Ruth Redding on why transformation and AI programmes fail without genuine adoption, and how leaders can build 'Adoption Insurance' into change from day one | READ FULL ARTICLE
by Darren Sheppard • 18 June 2026
Procurement teams that invite structured external challenge — not resist it — build stronger, more defensible decisions. Learn how to use market testing and early supplier engagement to strengthen procurement authority, not undermine it | READ NOW
SHOW MORE