Case Study: Enhancing Data Centre Infrastructure through a Comprehensive Connectivity Study



Subscribe Contact us

We were approached by one of the fastest growing data centre providers in Europe. With over 20 data centres throughout the continent, they are consistently meeting the need for scalable, high-performance infrastructure.


Despite this, a key data centre in Scandinavia had become reliant on a single, non-redundant 1 Gbps internet service from a local provider, posing significant risks to operational continuity. To enhance the reliability of its network and resolve these risks, our client needed to establish additional connectivity paths to ensure the redundancy of its infrastructure. 


The Ask


Cambridge Management Consulting was engaged to address these connectivity challenges by identifying and evaluating potential vendors and infrastructure options to create second and third connectivity paths. This involved exploring various types of connectivity, including internet access, point-to-point capacity, wavelengths, and dark fibre. 


Additionally, Cambridge MC was asked to provide recommendations for building a local fibre network around the data centre to control and maintain diverse paths. This would allow the data centre to connect directly to nearby points of presence (PoPs) and reduce dependency on external providers, thereby enhancing network resilience and operational control.


The goal of this project was to ensure that the Nordic data centre could maintain continuous operations even in the event of a failure in the primary connection.


Approach & Skills


Cambridge MC approached the project with a focus on ensuring operational continuity and resilience for the data centre. By identifying multiple connectivity paths, we aimed to mitigate the risk of network failures and ensure that the data centre could maintain continuous operations even in the event of a failure in the primary connection. This approach allowed Cambridge MC to provide a comprehensive solution to address both immediate and long-term connectivity needs.


We employed a combination of Agile and Waterfall methodologies to manage the project. The initial investigative phase allowed a Waterfall approach, in which our team conducted thorough research and analysis to identify potential vendors and connectivity options. This phase involved detailed interviews with various telecommunications providers and an assessment of publicly available information. 


Once the initial analysis was complete, the workflow transitioned to an Agile approach for the implementation phase. This allowed Cambridge MC to adapt to new information and feedback from stakeholders, ensuring that the final solution was both flexible and robust.


Challenges


  • Lack of information: One of the primary obstacles we faced was the lack of detailed network maps and information from some of the potential vendors. To overcome this, the team conducted extensive interviews with contacts at these companies and leveraged its existing network of industry contacts to gather as much information as possible.


  • Remote location: Another challenge was the remote location of the data centre, which limited the availability of local infrastructure and required us to explore creative solutions for connectivity. Cambridge MC addressed this by proposing the construction of a local fibre network around the data centre, which would allow for greater control and flexibility in connecting to nearby PoPs.


  • Fragmented factors: Additionally, coordinating with multiple vendors and ensuring that their services could be integrated seamlessly posed a logistical challenge. We mitigated this by recommending a phased approach to implementation, starting with the most critical connectivity paths and gradually expanding to include additional options. 


Outcomes & Results


  1. Increased Connectivity: Cambridge MC successfully identified and evaluated multiple connectivity paths for the data centre. By exploring various types of connectivity, including internet access, point-to-point capacity, wavelengths, and dark fibre, we provided a comprehensive solution that significantly enhanced network resilience and reliability.
  2. Greater Control & Flexibility: Our recommendations for building a local fibre network around the data centre allowed for greater control and flexibility in connecting to nearby points of presence, ensuring continuous operations even in the event of a failure in the primary connection. 
  3. New Vendors: The team’s extensive network of industry contacts and deep understanding of the regional telecommunications landscape allowed for a thorough and nuanced evaluation of potential vendors and connectivity options.
  4. Scope for Future Work: Cambridge MC identified several future developments with the potential to further enhance international connectivity and provide additional redundancy for the data centre. We also proposed further assistance, including a site visit for a more in-depth analysis of options, issuing RFI/RFP to vendors for capacity and fibre, and conducting similar connectivity studies for other candidate sites in the region. 
DOWNLOAD CASE STUDY

Get in touch with Our Consultants today


Contact - LightRiver Case Study

Subscribe to our Newsletter

Blog Subscribe

SHARE CONTENT

A representation of agent boxes (prompts) linked into a workflow on a computer screen.
by Charlotte Patrick • 9 November 2026
RESEARCH & ANALYSIS | Cambridge AIQ assesses 13 vendors delivering agentic AI for service assurance, comparing four distinct strategies and the key factors operators must weigh | READ PREVIEW & PURCHASE REPORT
Audience at the recent launch event for the #21toWatch 2027 awards at the Glasshouse, Cambridge.
9 November 2026
A new monthly event series for scaleup founders, investors, and advisers at The Glasshouse, Cambridge. Starts 26 November with CMR Surgical’s Martin Frost CBE | READ FULL PRESS RELEASE
Visualisation of Earth with lines of data wrapped around it
by Eric Green • 4 November 2026
PROCUREMENT & AI | Neoscalers often buy the network last, under pressure. Eric Green explains the contract-term and cost risks, and how procurement discipline closes the gap | READ FULL ARTICLE NOW
30 October 2026
23 October 2026, Cambridge – Cambridge Management Consulting (Cambridge MC) has celebrated its annual corporate Green Day, bringing colleagues together for a day of environmental volunteering instead of a day in the office. On Friday 23 October, the international management consultancy, headquartered in Cambridge, teamed up with Cambridge City Council to improve wildlife habitat at Cherry Hinton Hall, a 12-hectare public park in south-east Cambridge. Working alongside the City Council’s Community Engagement team, the Cambridge MC team focused on the glade in the nature area at the rear of the park, cutting back grass, clearing away the cuttings, and sowing wildflower seeds. The work was designed to support the management of the green space and create better conditions for wildlife, while giving Cambridge MC colleagues a direct role in caring for their local environment. Tim Passingham, founder and executive chairman of Cambridge MC, explained: “Making a positive impact means being prepared to roll up our sleeves and contribute to the communities in which we work. Rather than treating environmental responsibility as an abstract corporate ambition, Green Day gives our colleagues the opportunity to contribute their time and effort to community green spaces – turning our commitment into something tangible by working alongside our local community, supporting the places we share and recognising that small, practical actions can make a difference when we take them together. “The initiative also reflects the importance of collaboration in environmental action. Individual volunteers, community groups, businesses, and local authorities all have an important role to play in maintaining accessible green spaces and supporting urban biodiversity.” While Cambridge was the focus of the company-wide initiative, Green Day extended beyond the city, with events taking place in the New Forest, and planned initiatives in London which were unfortunately cancelled due to adverse weather. In the New Forest, Cambridge MC colleagues worked with local environmental group ECO SWAY on preparing shared green spaces and planting pollinator-friendly bulbs to support bees and butterflies in the spring. Unfortunately, the London team’s efforts were cancelled due to Storm Austen, however they were excited to be joining local volunteers from Stoke Newington Urban Green (SNUG) to water and mulch young trees ahead of winter, helping them to establish and reach maturity. As an international consultancy, the team’s environmental efforts did not stop there. In France, one Managing Partner contributed to his local ecosystem by planting an oak tree, and in Portugal another Partner showed her support by planting several fruit trees. Elsewhere, consultants based outside of the UK or simply unable to travel to the three primary locations sowed tree bombs as a remote way of amplifying the day’s overall mission. Green Day forms part of Cambridge MC’s wider commitment to using its expertise, time, and resources to create positive impact. The purpose-beyond-profit company commits at least 10% of its profits to charitable causes that tally with its ‘Five Cs’: Children (and young people), Conservation (and sustainability), Cancer, Communications, and Cambridge (the Cambridge ecosystem). Alongside financial support, Cambridge MC also engages in purposeful pro bono work, gifting at least 1% of its time and expertise to help charities mature, digitalise, and reduce costs. And, uniquely, the company holds 1% of its equity in reserve for charitable use should an equity event occur. In September, Cambridge MC achieved Certified B Corporation status, marking a significant milestone in the company’s commitment to responsible business and recognising its approach to creating value for its team, clients, community, and the environment alongside commercial success. Tim said: “Our approach recognises that a responsible business is not defined solely by the advice it gives clients, but also by the contribution it makes to the communities and environments in which it operates. “By combining hands-on work with local partners across Cambridge and the New Forest, the Green Day initiative is bringing this principle to life – one green space at a time.”
A neon wireframe view of a city with roads and bridges.
by Paul Brooker • 15 October 2026
Sales Transformation | Manual workarounds and fragmented systems are costing telecom operators revenue and margin. Discover how to remove the Complexity Tax and unlock value | READ FULL ARTICLE NOW
Statue of justice with neon overlay.
by Greg Mook • 7 October 2026
Greg Mook sets out the ten capabilities communications providers need for effective compliance, from business accountability to delivery-chain assurance | READ FULL ARTICLE
Sunrise over the ocean.
24 September 2026
Cambridge Management Consulting has achieved Certified B Corporation status, validating its commitment to responsible business and long-term stakeholder value | READ THE FULL PRESS RELEASE
A long  bank of solar panels in a field at dusk
by Scott Armstrong • 4 August 2026
ESOS Phase 4 isn't just compliance. Scott Armstrong explains why cheap audits cost more long-term, and how to treat Phase 4 as a strategic energy opportunity | READ FULL ARTICLE
Neon waves and lines with overlay of white plus signs, some dissolving away
by Jason Jennings • 14 July 2026
Procurement | Most organisations are sitting on 3–8 per cent of recoverable third-party spend. Here's where AI-powered spend analysis finds it — and how CFOs can act without cutting into operations | READ FULL ARTICLE
More posts